Objective. Students will set stair gauges on a framing square to calculated rise and run values and step off a full stringer layout on a 2×12 board, keeping all layout lines within 1/16 inch of correct position.
This lesson, its worked examples and its practice questions has not yet been verified by a licensed professional engineer or master tradesperson or by a certification or approval body. It is a study draft and may contain errors. Do not use it as instructions for work on a job site or on live equipment. Always follow your instructor, your supervising professional, and current official references and regulations.
VoTechWorks program approval and accreditation are still in progress. Credentials are issued only by the certifying bodies named in each program, after their own exams.
A staircase is only as safe and comfortable as the precision of its stringer layout. Inconsistent riser heights or tread depths cause people to trip — a leading cause of fall injuries on construction sites and in finished buildings. Every rise and run mark you scribe must be within 1/16 inch of the calculated dimension. That is not a suggestion; it is the pass standard for this lesson and a real-world professional expectation.
A framing square (also called a steel square or carpenter's square) is an L-shaped steel or aluminum tool with two arms: the blade (the longer, wider arm, typically 24 inches) and the tongue (the shorter, narrower arm, typically 16 inches). Both arms carry inch graduations on their faces and backs. For stair layout, you read the tongue for the rise and the blade for the run.
The body of the square can also be used with a stair gauge set — small brass fixtures that clamp to the edges of the square and act as stops. Once set, they let you slide the square along the board and scribe identical rise and run marks repeatedly without re-measuring each step.
Stair gauges are small brass or steel clamps, sold in pairs, that lock onto the edge of the framing square with a set-screw. One gauge is clamped to the tongue at the unit rise dimension; the other is clamped to the blade at the unit run dimension. The gauges rest against the top edge of the 2×12 stringer board as you step the square down the board. This guarantees each step is positioned from the same reference, eliminating cumulative error.
Setting stair gauges — key points:
When you step off a stringer, the first (bottom) riser height must be reduced by the thickness of one tread. This is because every riser above the first sits on top of a tread, raising its effective height by the tread thickness. The bottom step does not sit on a tread — it sits directly on the floor. If you do not make this reduction, the bottom riser will be taller than every other riser, which is a code violation and a tripping hazard.
For 1-inch nominal tread stock (actual 3/4 inch), reduce the bottom riser by 3/4 inch. For 2-inch nominal tread stock (actual 1-1/2 inches), reduce by 1-1/2 inches.
At the top of the stringer, the plumb cut (vertical cut) must align with the header or landing, not just fall wherever the last step happens to end. After stepping off all risers, check that your top plumb line lands correctly relative to the top of the stringer. In most framed stair assemblies, the top cut is a simple plumb line that allows the stringer to bear against the header. Verify this line is square (plumb) using the rise dimension on the tongue of your framing square.
1. Calculate your unit rise and unit run. Confirm the total rise and total run for the stair, then determine unit rise (total rise ÷ number of risers) and unit run (tread depth minus nosing, if applicable).
2. Set stair gauges. Clamp one gauge to the tongue at the unit rise dimension and the other to the blade at the unit run dimension. Tighten both set-screws.
3. Position the square at the bottom of the stringer. Place the 2×12 flat on sawhorses, crown edge up. Position the framing square near the lower end of the board with both gauges resting against the top edge.
4. Scribe the first step. Draw a line along the tongue (rise line) and a line along the blade (run line). The intersection is the nosing corner of the tread.
5. Step off. Slide the square up the board so the blade gauge rests against the top edge at the end of the previous run line. Scribe the next rise and run. Repeat for all steps.
6. Mark the bottom reduction. Measure down from the bottom riser line by the tread thickness and re-draw the cut line. This is your actual bottom cut.
7. Verify the top cut. Confirm the final plumb line at the top aligns with your header location.
8. Check all marks. Use a tape and combination square to verify every riser height and run depth. Any mark more than 1/16 inch off must be redrawn in red and corrected.
Use a combination square set to the unit rise to spot-check each riser mark. Use a tape measure to check each run. Mark any out-of-tolerance lines in red pencil so they stand out. Re-set the framing square from the nearest correct line and redraw. Do not erase and guess — start the verification from a confirmed good point.
Answer each question, then check it. Nothing is recorded; this is your own practice.
A free tech program — complimentary, as our commitment to get America working. Help us build VoTechWorks. Tell us what works, what doesn’t, and what you want to learn.
Does the school offer financial aid?
No. We don’t offer financial aid because we’re free. No, really: completely free.
Do you offer industry certification?
No. We are not certified yet, so we can’t offer that to students. What we do offer is knowledge and understanding of a trade.
Enroll first in the trade you’re interested in. You get your key, your program opens, and you begin studying.
Enroll free →